Implementation Concept

Hotel System Go-Live

Concept project · Fictional hotel, people, and figures

A live operating dashboard for a 180-room hotel property management system (PMS) implementation, built around measurable goals, the critical path, cost tracking, risk ownership, and a go/no-go decision the GM can sign.

Open the live dashboard
Role
Role in scenario: Implementation lead
Context
Self-directed concept project
Year
2026

[ Problem ]

A percent-complete status deck can hide the two things that decide a go-live: what is on the critical path and who has to make the call. A hotel gets one opening weekend, so every risk needs an owner, a fallback, and a clear waiver path.

The real-world version of this for me was three partner launches at Rocket Travel, where I wrote the playbooks that moved each partner from launch into support. This scenario runs the implementation side end to end.

[ Approach ]

  • Defined five project goals with concrete pass bars, including interface certification, reservation reconciliation, and 14 successful night-audit closes.
  • Tracked the plan at about 10% over on hours and 13% behind schedule, then brought the owner’s representative two costed recovery options with a recommendation.
  • Scored risks by likelihood and impact, named the owner of each cause, and documented the fallback to use if a dependency slipped.
  • Built a 12-item go/no-go checklist with waiver authority on every line, supported by decision, issue, scope-change, and handoff logs.

[ Scenario outcome ]

  • The scenario holds its Nov 16 launch date through week 12, with two amber risks and recovery actions already booked.
  • All 1,236 pre-opening reservations reconcile after a SQL check catches 38 duplicated group bookings.
  • Configuration reaches 97% after narrowing launch rate plans from 34 to 18 to protect the schedule.
  • The Jan 15 handoff gives support the decisions, owners, and fallbacks behind the configuration.

[ Tools & skills ]

Technical Project LeadershipProject PlanningRisk ManagementChange ManagementCross-functional CoordinationSQLData ValidationSoftware ImplementationDocumentation